Page 84 - Microsoft Word - MoHR-ISP-D4-Final ISP-EXECUTIVE SUMMARY-v1.0
P. 84

MINISTRY OF HUMAN RESOURCES (MoHR)
                 ICT STRATEGIC PLAN 2014 - 2018



                 The  total  five-year  implementation  cost  is  estimated  at  RM
                 51,347,000.00.  The  said  cost  estimates  yearly  distribution  is  as  shown

                 below.













































                                           ISP Implementation Cost Estimates Per Year

                 The ISP cost estimates by program is as shown in the following diagram.

                 From the said chart, it can be seen that the highest contribution cost if
                 from  the  Program  2  –  Improve  ICT  Capabilities  and  Capacity,  and

                 followed  by  Program  1  –  Improve  Organisation  Capabilities  &  Service

                 Delivery. Program 3 – Enterprise Wide Optimisation, is the smallest cost
                 to  implement  as  the  said  program  capitalise  the  Central  Agency
                 initiatives and the cost is borne by the Central Agency, through MAMPU.








            ISP EXECUTIVE SUMMARY v1.0

                                                                                                       73
   79   80   81   82   83   84   85   86   87